1. Overview
The Disturbance Reporting function is used to record machine stoppages and production disturbances during manufacturing operations.
The system allows operators to:
- Register production interruptions
- Select the cause of the disturbance
- Track machine downtime automatically
- Store all disturbance events in the history table
Important: before a disturbance can be started, the current production operation must first be stopped and production quantities must be reported.
2. Stopping Production Before Disturbance Reporting
Before creating a disturbance report, the operator must:
- Stop the active production operation
- Report the completed quantity
- Save the production feedback
Only after production has been stopped can the disturbance process be started.
This ensures:
- Accurate production reporting
- Correct production time calculation
- Precise downtime tracking
3. Starting a Disturbance
To start a disturbance, click the red Disturbance Report button.
Disturbance button
After clicking the button, the disturbance reporting screen becomes available.
4. Disturbance Reporting Screen
Disturbance reporting screen
The screen contains the following fields:
Resource
Displays the selected machine or resource currently affected by the disturbance.
Example:
- 3D – K2 Pro Combo
Cause of Disturbance
The operator must select the reason for the machine stoppage from the dropdown list.
Cause selection
Example causes:
- Machine Failure
- Material Shortage
Short Text Description of the Disturbance
Optional text field where the operator can enter additional information about the problem or stoppage.
5. Starting the Disturbance Timer
After selecting the disturbance cause, the operator must click the Start button.
The system then:
- Starts the disturbance process
- Automatically records the start time
- Calculates the total downtime in the background
The machine remains in disturbance status until it is released again.
6. Ending the Disturbance
The disturbance can only be stopped by a user with administrator privileges.
To release the machine:
- An administrator opens the disturbance screen
- Clicks the Stop button
- The system records the end of the disturbance
This ensures controlled restart authorization and prevents unauthorized machine releases.
7. Automatic Downtime Calculation
While the disturbance is active, the system continuously calculates:
- Start time of disturbance
- End time of disturbance
- Total downtime duration
The downtime calculation is fully automatic.
8. Disturbance History Table
All disturbances are stored in the table at the bottom of the screen.
The table records:
- Resource ID
- Resource Name
- Cause of Disturbance
- Start of Disturbance
- End of Disturbance
- Days Spent in Disturbance
This provides full traceability for:
- Machine downtime
- Production interruptions
- Maintenance analysis
- OEE calculations
9. Important Notes
- Production must always be stopped before starting a disturbance.
- Disturbance timers start only after the Start button is pressed.
- Only administrators can stop and release a disturbance.
- Every disturbance event is automatically logged in the history table.
- Disturbance reporting supports accurate production tracking and downtime analysis.